AS ON 01.03.2026

    TOWER-1
  • Internal repairing & retrofitting works in progress (Ground to 18th Floor).
  • Extension area 12th floor slab completed.
  • Internal electrical works in progress (1st - 2nd Floor).
    TOWER-2
  • Internal repairing & retrofitting works in progress (Ground to 16thFloor).
  • Extension area 12th floor slab completed.
  • Internal electrical works in progress (1st - 2nd Floor).
    TOWER-3
  • Internal repairing & retrofitting works in progress (Ground to 19th Floor).
  • Internal electrical works in progress (6th - 9th Floor).
    TOWER-4
  • Internal repairing & retrofitting works in progress (Ground to 14th Floor).
  • Internal electrical works in progress (5th - 9th Floor).
    TOWER-5
  • Internal repairing & retrofitting works in progress (Ground to 2nd, 7th to 18th Floor).
  • Internal electrical works in progress (7th – 9th Floor).
    TOWER-6
  • Initial test pile done.
    TOWER-7
  • Piling work completed.
    NON-TOWER
  • Podium slab & retaining wall dismantling in progress.
  • Raft extension works in progress.
  • Foundation works for commercial & podium in progress.
  • Ground floor & 1st floor slab in progress.