AS ON 01.03.2026
TOWER-1
Internal repairing & retrofitting works in progress (Ground to 18th Floor).
Extension area 12th floor slab completed.
Internal electrical works in progress (1st - 2nd Floor).
TOWER-2
Internal repairing & retrofitting works in progress (Ground to 16thFloor).
Extension area 12th floor slab completed.
Internal electrical works in progress (1st - 2nd Floor).
TOWER-3
Internal repairing & retrofitting works in progress (Ground to 19th Floor).
Internal electrical works in progress (6th - 9th Floor).
TOWER-4
Internal repairing & retrofitting works in progress (Ground to 14th Floor).
Internal electrical works in progress (5th - 9th Floor).
TOWER-5
Internal repairing & retrofitting works in progress (Ground to 2nd, 7th to 18th Floor).
Internal electrical works in progress (7th – 9th Floor).
TOWER-6
Initial test pile done.
TOWER-7
Piling work completed.
NON-TOWER
Podium slab & retaining wall dismantling in progress.
Raft extension works in progress.
Foundation works for commercial & podium in progress.
Ground floor & 1st floor slab in progress.