AS ON 01.12.2025
TOWER-1
Internal Repairing & Retrofitting Works in Progress (Ground to 16thFloor).
Extension Area 18th floor slab completed.
TOWER-2
Internal Repairing & Retrofitting Works in Progress (Ground to 16thFloor).
Extension Area 11th floor slab completed.
TOWER-3
Internal Repairing & Retrofitting Works in Progress (Ground to 18th Floor).
Internal Electrical works in progress (6th - 8th Floor).
TOWER-4
Internal Repairing & Retrofitting Works in Progress (Ground to 14th Floor).
Internal Electrical works in progress (5th - 8th Floor).
TOWER-5
Internal Repairing & Retrofitting Works in Progress (Ground to 2nd, 7th to 18th Floor).
Internal Electrical works in progress (7th – 9thFloor).
TOWER-7
Piling Work in progress.
NON-TOWER
Podium Slab & Retaining Wall Dismantling in progress.
Raft Extension Works in Progress.
Foundation works for Commercial Block in progress.
Ground Floor & 1st Floor Slab in progress .