AS ON 01.09.2025

    TOWER-1
  • Internal Repairing & Retrofitting Works in Progress (Ground to 15thFloor).
  • Extension Area 11th Floor Slab Completed.
    TOWER-2
  • Internal Repairing & Retrofitting Works in Progress (Ground to 14thFloor).
  • Extension Area 7th Floor Slab Completed.
    TOWER-3
  • Internal Repairing & Retrofitting Works in Progress (Ground to 16th Floor).
  • Internal Electrical works in progress (6th-7th Floor).
    TOWER-4
  • Internal Repairing & Retrofitting Works in Progress (Ground to 14th Floor).
  • Internal Electrical works in progress (5th-7th Floor).
    TOWER-5
  • Internal Repairing & Retrofitting Works in Progress (Gr, 7th to 18th Floor).
  • Internal Electrical works in progress (7th Floor).
    TOWER-6
  • Initial Test Pile done.
    TOWER-7
  • Initial Test Pile done.
    NON-TOWER
  • Podium Slab Dismantling in Progress.
  • Raft Extension Works in Progress.
  • Foundation works for Commercial Block in progress.
  • Ground Floor Slab in progress.