AS ON 01.09.2025
TOWER-1
Internal Repairing & Retrofitting Works in Progress (Ground to 15thFloor).
Extension Area 11th Floor Slab Completed.
TOWER-2
Internal Repairing & Retrofitting Works in Progress (Ground to 14thFloor).
Extension Area 7th Floor Slab Completed.
TOWER-3
Internal Repairing & Retrofitting Works in Progress (Ground to 16th Floor).
Internal Electrical works in progress (6th-7th Floor).
TOWER-4
Internal Repairing & Retrofitting Works in Progress (Ground to 14th Floor).
Internal Electrical works in progress (5th-7th Floor).
TOWER-5
Internal Repairing & Retrofitting Works in Progress (Gr, 7th to 18th Floor).
Internal Electrical works in progress (7th Floor).
TOWER-6
Initial Test Pile done.
TOWER-7
Initial Test Pile done.
NON-TOWER
Podium Slab Dismantling in Progress.
Raft Extension Works in Progress.
Foundation works for Commercial Block in progress.
Ground Floor Slab in progress.