ERROR:
Javascript not activated
×
AS ON 01.02.2025
TOWER-1
2nd floor slab casting done & ground flloor brick work in progress.
TOWER-2
Part ground floor slab completed.
Part 1st floor slab casting done.
Balance part ground floor slab shuttering work in progress.
Ground floor anchor - 2 wall reinforcement binding, shuttering and casting progress.
TOWER-3
Roof slab casting done.
Above roof work in progress.
Finishing work in progress.
Model flat completed.
TOWER-4
11th floor level slab completed.
Roof slab shuttering work in progress.
Upto 3rd floor brickwork & 3rd floor plaster done .
Internal plumbingwork in progress.
TOWER-5
Roof slab casting done.
Upto 9th floor brick work done.
10th floor brick work in progress.
1st to 8th floor plaster work completed.
9th floor plaster work in progress.
TOWER-6
6th floor slab casting done.
7th floor level slab mivan shuttering work in progress.
3rd floor brick work and plaster completed.
TOWER-7
Roof slab completed.
Above roof work in progrss
Internal plumbing work in progrss.
Water proofing work in progress.
Flooring work in progress.