AS ON 01.02.2025

    TOWER-1
  • 2nd floor slab casting done & ground flloor brick work in progress.
    TOWER-2
  • Part ground floor slab completed.
  • Part 1st floor slab casting done.
  • Balance part ground floor slab shuttering work in progress.
  • Ground floor anchor - 2 wall reinforcement binding, shuttering and casting progress.
    TOWER-3
  • Roof slab casting done.
  • Above roof work in progress.
  • Finishing work in progress.
  • Model flat completed.
    TOWER-4
  • 11th floor level slab completed.
  • Roof slab shuttering work in progress.
  • Upto 3rd floor brickwork & 3rd floor plaster done .
  • Internal plumbingwork in progress.
    TOWER-5
  • Roof slab casting done.
  • Upto 9th floor brick work done.
  • 10th floor brick work in progress.
  • 1st to 8th floor plaster work completed.
  • 9th floor plaster work in progress.
    TOWER-6
  • 6th floor slab casting done.
  • 7th floor level slab mivan shuttering work in progress.
  • 3rd floor brick work and plaster completed.
    TOWER-7
  • Roof slab completed.
  • Above roof work in progrss
  • Internal plumbing work in progrss.
  • Water proofing work in progress.
  • Flooring work in progress.