AS ON 01.08.2023

    CLUSTER 01(ROW HOUSE NO. 298-303 ):
  • Civil sub structure work completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 02(ROW HOUSE NO. 290,291 ):
  • Civil sub structure work completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 03(ROW HOUSE NO. 292-297):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 04(ROW HOUSE NO. 288,289):
  • Civil sub structure work completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 05(ROW HOUSE NO. 285-287 ):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 06(ROW HOUSE NO. 271-284):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 07(ROW HOUSE NO. ):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 08(ROW HOUSE NO. 254-259):
  • Civil sub structure work completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 09(ROW HOUSE NO. 260-270):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 10(ROW HOUSE NO. 248-253):
  • Civil sub structure work completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
  • Inside & outside area plaster under progress.
    CLUSTER 11(ROW HOUSE NO. 229-236 ):
  • Civil sub structure work completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 12(ROW HOUSE NO. 221-228):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Window work under progress. 
  • Internal putty work under progress. 
  • Tiling work completed. 
  • Plumbing work completed.
  • Internal electrification work completed. 
  • External plastering work completed. 
    CLUSTER 13(ROW HOUSE NO. 216-220):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Window work completed. 
  • Tiling work completed. 
  • Internal electrification work completed. 
  • Plumbing work completed.
  • External plastering work completed  
    CLUSTER 14(ROW HOUSE NO. 199-210):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Door shutter work under progress.
  • Window work completed. 
  • Internal putty work under progress. 
  • Tiling work completed. 
  • Plumbing work completed.
  • Internal electrification work completed. 
  • External plastering work completed & external painting work under progress. 
    CLUSTER 15(ROW HOUSE NO. 211-215):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Window work under progress. 
  • Plumbing works completed. 
  • Internal putty work completed. 
  • Tiling works under progress.
  • Internal electrification work completed. 
  • External plastering works completed & external painting works under progress. 
    CLUSTER 16(ROW HOUSE NO. 187-198):
  • Civil sub structure work completed.
  • Civil super structure completed for Phase I unit & under progress for other Phases.
  • Internal brick works & plastering completed for Phase I units & under progress for other Phases.
  • Door frame fixing work completed for Phase I unit.
  • Window work completed for phase I unit.
  • Internal putty work under progress.
  • Tiling works completed for Phase I unit & under progress for other Phases.
  • Plumbing work completed.
  • Internal electrification work completed.
  • External plastering work completed for Phase I unit & external painting for phase I unit under progress.
    CLUSTER 17(ROW HOUSE NO. 178-186):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Window work under progress. 
  • Internal Plumbing work completed. 
  • Internal putty work under progress. 
  • Internal electrification work under progress.
  • External plastering work completed.
    CLUSTER 18(ROW HOUSE NO. 158-162):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed.
  • Window work under progress.
  • Internal putty work under progress.
  • Tiling works under progress.
  • Plumbing work under progress.
  • Internal electrification work completed.
  • External plastering work completed.
    CLUSTER 19(ROW HOUSE NO. 163-167):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed.
  • Door shutter work under progress.
  • Window work completed.
  • Internal putty work completed.
  • Tiling work completed.
  • Plumbing work completed.
  • Internal electrification work completed.
  • External plastering work & external painting work under progress.
    CLUSTER 20(ROW HOUSE NO. 168-177):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Door shutter work under progress.
  • Window work completed. 
  • Internal putty work completed. 
  • Tiling work completed. 
  • Plumbing work completed.
  • Internal electrification work completed. 
  • External plastering works completed & external painting works under progress.
    CLUSTER 21(ROW HOUSE NO. 153-157):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed. 
  • Window work under progress. 
  • Internal putty works under progress. 
  • Tiling work under progress. 
  • Plumbing work under progress.
  • Internal electrification work under progress. 
  • External plastering work completed.
    CLUSTER 22(ROW HOUSE NO. 148-152):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed.
  • Door shutter work completed.
  • Window work completed.
  • Plumbing work completed.
  • Internal electrification work completed.
  • External plastering work & external painting work completed.
    CLUSTER 23(ROW HOUSE NO. 138-147):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed. 
  • Door shutter work under progress.
  • Window work completed. 
  • Internal putty work under progress. 
  • Tiling work completed. 
  • Plumbing work completed.
  • External plastering work completed and external painting work under progress. 
    CLUSTER 24(ROW HOUSE NO. 117 ):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 26(ROW HOUSE NO. 118-127):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed & under progress for other Phases.
  • Door frame fixing work completed & under progress for other Phases.
  • Door shutter work completed.
  • Window work completed & under progress for other Phases.
  • Internal putty work completed & under progress for other Phases.
  • Tiling work completed & under progress for other Phases.
  • Plumbing work completed & under progress for other Phases.
  • Internal electrification work completed & under progress for other Phases.
  • External plastering work & painting work completed & under progress for other Phases.
    CLUSTER 27(ROW HOUSE NO. 107-115):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed & under progress for other Phases.
  • Door shutter work completed & under progress for other Phases.
  • Window work completed & under progress for other Phases.
  • Internal putty work completed & under progress for other Phases.
  • Tiling work under completed & under progress for other Phases.
  • Plumbing work completed & under progress for other Phases.
  • Internal electrification work completed & under progress for other Phases.
  • External plastering work & painting work completed & under progress for other Phases.
    CLUSTER 28(ROW HOUSE NO. 128-137):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed 
  • Door shutter work under progress.
  • Window work under progress. 
  • Internal putty work under progress. 
  • Tiling work under progress. 
  • Plumbing work completed.
  • Internal electrification work progress.
  • External plastering work completed and external painting work under progress. 
    CLUSTER 29(ROW HOUSE NO. 98-106):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed. 
  • Door frame fixing work completed 
  • Window work completed. 
  • Internal putty work under progress. 
  • Tiling work under progress. 
  • Plumbing work completed.
  • Internal electrification work completed.
  • External plastering work completed. 
    CLUSTER 33(ROW HOUSE NO. 71-81):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed.
  • Door shutter work completed.
  • Window work completed.
  • Internal putty work completed.
  • Tiling work completed.
  • Plumbing work completed.
  • Internal electrification work completed.
  • External plastering work completed & painting work completed.
    CLUSTER 34(ROW HOUSE NO. 53-64):
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed.
  • Door shutter work completed.
  • Window work completed.
  • Internal putty work completed.
  • Tiling work completed.
  • Internal electrification work completed.
  • Plumbing work completed.
  • External plastering work completed & painting work completed.
    CLUSTER 35(ROW HOUSE NO. 82-90):
  • Civil sub structure work completed for Phase I & under progress for other phases.
  • Civil super structure work completed for phase I & under progress for other phases
  • Internal brick works & plastering work completed for Phase I & under progress for other phases. 
  • Internal electrification work completed for Phase I & under progress for other phases.
  • Door frame work completed for Phase I & under progress for other phases. 
  • Window work under progress I & under progress for other phases.
  • Tiling work completed I & under progress for other phases. 
  • Plumbing work completed I & under progress for other phases.
  • External plastering work completed I & under progress for other phases. 
  • External plastering work completed & external painting work under progress.
    CLUSTER 36(ROW HOUSE NO. 43-52):
  • Civil sub structure work completed for Phase I & under progress for other phases.
  • Civil super structure work completed for phase II & under progress for other phases.
  • Internal brick works & plastering work completed for Phase II & under progress for other phases. 
  • Window work under progress Phase I & other phases.
  • Plumbing work under completed Phase I & under progress for other phases. 
  • External plastering work completed Phase I & under progress for other phases. 
    CLUSTER 37(ROW HOUSE NO. 25-32):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 38(ROW HOUSE NO. 33-40):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 39(ROW HOUSE NO. 1-11):
  • Civil sub structure works completed.
  • Civil super structure work completed.
  • Internal brick work & plastering work completed.
  • Door frame fixing work completed.
  • Door shutter work completed.
  • Window work completed.
  • Internal putty work completed.
  • Tiling work completed.
  • Internal electrification work completed.
  • Plumbing work completed.
  • External plastering work completed & painting work completed.
    CLUSTER 43(ROW HOUSE NO. 22 ):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 44(ROW HOUSE NO. 23 ):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 45(ROW HOUSE NO. 24):
  • Civil sub structure work under completed.
  • Civil super structure work under progress.
  • Internal brick work under progress. 
    CLUSTER 46(ROW HOUSE NO. 65-70 ):
  • Civil sub structure work under completed.
  • Civil super structure works completed.
  • Internal brick work under progress. 
  • Inside & outside area plaster under progress.
    Club:
  • Civil sub structure work completed.
  • Civil super structure work completed.
  • Roof floor slab casting completed
  • Internal brick work completed for inside & outside area plaster completed.
  • Window work completed.
  • Plumbing work completed.
  • External plastering work completed.
  • Finishing work under progress.