AS ON 01.06.2023

    BLOCK-B(WING-1)
  • External paint work is in progress.
    BLOCK-B(WING-2)
  • Paintwork is in progress at the club.
  • External paint work is in progress.
    BLOCK-C
  • Piling work in progress.
     BLOCK-A
  • The 11th-floor Internal Plaster work is completed.
  • External Plastering work in progress.
  • The 9th-floor Tiles work is completed, 10th & 11th-floor work is in progress.
  • The 10th-floor Internal Ceiling work is completed & 11th-floor work is in progress.
  • Internal Wall Putty work is completed up to the 6th floor & 7th-floor work is in progress.

  • INFRASTRUCTURE WORK:
  • Underground reservoir completed.
  • Rainwater Harvesting 1 no tank completed & 1 no work in progress.
  • STP civil work is completed. Electro-Mechanical work in progress.
  • Road work in progress.
  • Landscape work on progress.