AS ON 04.01.2023

    Tower - 2
  • Piling Work is completed.
  • Foundation work is in progress (95% done).
  • 1st floor slab work is in progress (35% done).
    Tower - 3
  • Piling Work is completed.
  • Foundation work is completed.
  • 1st floor slab casting is completed.
  • 2nd floor slab casting is completed.
  • 3rd floor slab casting is completed.
  • 4th floor slab in progress (Shuttering reinforcement 90% done).