AS ON 01.09.2023
BLOCK-29
10th floor slab casting & 3rd - 4th floor brickwork are in progress.
BLOCK-34
6th - 7th floor flooring work are in progress.
BLOCK-35
8th - 9th floor internal plaster work are in progress.
BLOCK-36
Foundation completed and 2nd floor slab casting work in progress.
BLOCK-38
11th - 12th floor brick work in progress.
7th floor internal plaster & 3rd - 6th floor flooring work are in progress.