AS ON 01.05.2022

    BLOCK-22
  • External plaster completed.
  • Tiles work in progress.
    BLOCK-24
  • 7th floor brick work completed.
  • 5th floor and 7th inside plaster completed.
  • External plaster work in progress.
    BLOCK-25
  • External plaster completed.
  • Tiles work in progress.
    BLOCK-6
  • Pile cap work in progress.
    BLOCK-7
  • Pile work completed.
    BLOCK-8
  • Pile work in progress.