AS ON 01.05.2026

    BLOCK-2
  • 1st floor column Shuttering, reinforcement Work In Progress.
    BLOCK-3
  • 6th floor slab reinforcement Work In Progress.
  • 3rd floor brick work in progress.
  • 6th floor slab is getting ready for casting.
    BLOCK-4
  • Above Roof structure work in progress.
  • External plaster Work in progress.
  • 7th floor waterproofing work in progress.
    BLOCK-5
  • Roof waterproofing work in progress.
  • External primer Work in Progress.
    BLOCK-6
  • Ground floor parking marking work in Progress.
    BLOCK-7
  • Ground floor Flat GB internal Brick Work completed.
  • Internal Flooring and door window fixing work completed.
  • Ground floor parking marking work in Progress.
    BLOCK-8
  • Quality snagging work in progress.
  • Ground floor parking painting work in Progress.
  • Ground floor Flat GB internal Brick Work completed.
  • Internal Flooring and door window fixing work completed.
    BLOCK-9
  • Lift installation work In progress.
  • Internal Flat Door work in progress.
  • 3rd floor Tiles work in progress.
  • 4th floor to 7th floor flooring work completed.