AS ON 01.05.2025

    BLOCK-2
  • Piling work in progress.
    BLOCK-3
  • Ground floor column tie beam reinforcement work in progress.
  • Shuttering and casting work in progress.
    BLOCK-4
  • 6th floor column reinforcement, shuttering work in progress.
  • 1st floor brick work in progress.
    BLOCK-5
  • Above roof floor work in progress.
  • Waterproofing work in progress.
  • 6th & 7th Floor plaster work in progress.
  • External plaster in progress.
    BLOCK-6
  • Snagging in progress.
    BLOCK-7
  • Above roof floor work in progress.
  • External Paint work in progress..
    BLOCK-8
  • Above roof floor work in progress.
  • External primer Work in Progress.
  • 1st floor flooring work in progress.
    BLOCK-9
  • Waterproofing work in progress.
  • Above Roof Floor work in progress.
  • 7th floor plaster in progress.
  • External plaster in progress.