AS ON 01.05.2022
BLOCK-22
External plaster completed.
Tiles work in progress.
BLOCK-24
7th floor brick work completed.
5th floor and 7th inside plaster completed.
External plaster work in progress.
BLOCK-25
External plaster completed.
Tiles work in progress.
BLOCK-6
Pile cap work in progress.
BLOCK-7
Pile work completed.
BLOCK-8
Pile work in progress.