AS ON 01.05.2025
BLOCK-2
Piling work in progress.
BLOCK-3
Ground floor column tie beam reinforcement work in progress.
Shuttering and casting work in progress.
BLOCK-4
6th floor column reinforcement, shuttering work in progress.
1st floor brick work in progress.
BLOCK-5
Above roof floor work in progress.
Waterproofing work in progress.
6th & 7th Floor plaster work in progress.
External plaster in progress.
BLOCK-6
Snagging in progress.
BLOCK-7
Above roof floor work in progress.
External Paint work in progress..
BLOCK-8
Above roof floor work in progress.
External primer Work in Progress.
1st floor flooring work in progress.
BLOCK-9
Waterproofing work in progress.
Above Roof Floor work in progress.
7th floor plaster in progress.
External plaster in progress.