AS ON 01.11.2025

    BLOCK-2
  • Excavation, PCC, Pile cap reinforcement work in progress.
    BLOCK-3
  • 3rd floor column Shuttering, reinforcement work in progress.
    BLOCK-4
  • Above Roof structure work in progress.
  • 5th floor plaster work in progress.
    BLOCK-5
  • Above Roof structure work in progress.
  • External Plaster in progress.
    BLOCK-6
  • Parking floor work in progress.
    BLOCK-7
  • Parking floor work in progress.
    BLOCK-8
  • Lift Installation in progress.
  • Internal pop work in progress.
    BLOCK-9
  • Above roof waterproofing work in progress.
  • Ground floor work in progress.
  • Aluminium window work in progress.