AS ON 01.02.2026

    BLOCK-2
  • Ground floor column shuttering, reinforcement work In progress.
    BLOCK-3
  • 4th floor column shuttering, reinforcement work In progress.
  • 1st and 2nd floor brick work in progress.
    BLOCK-4
  • Above Roof structure work in progress.
  • 7th floor plaster work in progress.
    BLOCK-5
  • External plaster in progress.
  • External primer work in progress.
  • 7th floor tiles work in progress.
    BLOCK-6
  • Parking floor work in progress.
    BLOCK-7
  • Parking floor work in progress.
    BLOCK-8
  • Internal lobby area painting work in progress.
    BLOCK-9
  • Lift installation work In progress.
  • Ground floor work in progress.
  • Aluminum window work in progress.
  • 7th floor tiles work in progress.