AS ON 01.11.2025
BLOCK-2
Excavation, PCC, Pile cap reinforcement work in progress.
BLOCK-3
3rd floor column Shuttering, reinforcement work in progress.
BLOCK-4
Above Roof structure work in progress.
5th floor plaster work in progress.
BLOCK-5
Above Roof structure work in progress.
External Plaster in progress.
BLOCK-6
Parking floor work in progress.
BLOCK-7
Parking floor work in progress.
BLOCK-8
Lift Installation in progress.
Internal pop work in progress.
BLOCK-9
Above roof waterproofing work in progress.
Ground floor work in progress.
Aluminium window work in progress.