ERROR:
Javascript not activated
×
AS ON 01.11.2025
TOWER-1
3rd floor slab casting done.
Landscape area RCC wall working progress.
4th floor level slab shuttering & reinforcement working in progress.
Ground floor brick & plaster work completed.
1st floor brick & plaster work progress.
TOWER-2
Ground, 1st & 2nd floor slab casting completed
3rd floor level slab shuttering reinforcement working progress.
Ground floor anchor - 2 rcc wall & anchor - 1 inside brick work & plaster completed.
1st floor brick work & plaster in progress.
TOWER-3
Roof floor slab casting done.
Above roof work in progress.
Finishing work in progress.
Model flat completed.
Ground floor brick work & plaster working progress.
Out side paint working progress.
TOWER-4
Roof slab casting completed.
Upto 3rd floor brick work & 3rd floor plaster done.
Internal plumbingwork in progress.
above roof parapet wall reinforcement & shuttering work progress.
TOWER-5
Roof slab casting done.
Above roof parapet, over head tank completed.
Upto 10th floor brick work done.
1st to 10th floor plaster completed
11th floor brick & plaster working progress.
Ground floor to above roof height out side plaster in progress.
TOWER-6
10th floor slab casting done.
11th floor level slab reinforcement & mivan shuttering work in progress.
3rd floor brick work and plaster completed.
TOWER-7
Roof slab completed.
Above roof work in progrss
Internal plumbing work in progrss.
Water proofing work in progress.
Flooring work in progress.
Ground floor brick work & plaster working progress
Outside paint working progress .
PODIUM
Pile work in progress.
ROAD
Tower 6, Tower 3 & Tower 4 back side road working progress .
Tower 1, Tower 2 font side road work completed.