AS ON 01.11.2025

    TOWER-1
  • 3rd floor slab casting done.
  • Landscape area RCC wall working progress.
  • 4th floor level slab shuttering & reinforcement working in progress.
  • Ground floor brick & plaster work completed.
  • 1st floor brick & plaster work progress.
    TOWER-2
  • Ground, 1st & 2nd floor slab casting completed
  • 3rd floor level slab shuttering reinforcement working progress.
  • Ground floor anchor - 2 rcc wall & anchor - 1 inside brick work & plaster completed.
  • 1st floor brick work & plaster in progress.
    TOWER-3
  • Roof floor slab casting done.
  • Above roof work in progress.
  • Finishing work in progress.
  • Model flat completed.
  • Ground floor brick work & plaster working progress.
  • Out side paint working progress.
    TOWER-4
  • Roof slab casting completed.
  • Upto 3rd floor brick work & 3rd floor plaster done.
  • Internal plumbingwork in progress.
  • above roof parapet wall reinforcement & shuttering work progress.
    TOWER-5
  • Roof slab casting done.
  • Above roof parapet, over head tank completed.
  • Upto 10th floor brick work done.
  • 1st to 10th floor plaster completed 
  • 11th floor brick & plaster working progress.
  • Ground floor to above roof height out side plaster in progress.
    TOWER-6
  • 10th floor slab casting done.
  • 11th floor level slab reinforcement & mivan shuttering work in progress.
  • 3rd floor brick work and plaster completed.
    TOWER-7
  • Roof slab completed.
  • Above roof work in progrss
  • Internal plumbing work in progrss.
  • Water proofing work in progress.
  • Flooring work in progress.
  • Ground floor brick work & plaster working progress
  • Outside paint working progress .
    PODIUM
  • Pile work in progress.
    ROAD
  • Tower 6, Tower 3 & Tower 4 back side road working progress .
  • Tower 1, Tower 2 font side road work completed.