AS ON 01.04.2026
BLOCK-1 (TOWER A)
1. Sub Structure Work - 100% Done
2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
4. 2nd Slab With Mivan Setting Flats - Work in Progress.
BLOCK-1 (TOWER B)
1. Sub Structure Work - 100% Done
2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
4. 2nd Slab With Mivan Setting Flats - Work in Progress.
BLOCK-1 (TOWER C)
1. Sub Structure Work - 100% Done
2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
4. 2nd Slab With Mivan Setting Flats - Work in Progress.
BLOCK-2 (TOWER D)
1) Piling Work: - A) Piling - 183 Nos Done Out Of 189 Nos.
BLOCK-2 (TOWER E)
1) Piling Work: - A) Piling - 115 Nos Done Out Of 125 Nos.