AS ON 01.07.2026
BLOCK-1 (TOWER A)
1. Sub Structure Work - 100% Done
2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
4. 2nd Slab With Mivan Setting Flats - Work in Progress.
5. 2nd Slab With Conventional Area - 100 % Done.
6. 2nd Slab to 3rd Slab Level Column/Shear Wall- Work in progress.
BLOCK-1 (TOWER B)
1. Sub Structure Work - 100% Done
2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
4. 2nd Slab With Mivan Setting Flats - Work in Progress.
5. 2nd Slab With Conventional Area - 100 % Done.
6. 2nd Slab to 3rd Slab Level Column/Shear Wall- Work in progress.
BLOCK-1 (TOWER C)
1. Sub Structure Work - 100% Done
2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
4. 2nd Slab With Mivan Setting Flats - Work in Progress.
5. 2nd Slab With Conventional Area - 100 % Done.
6. 2nd Slab to 3rd Slab Level Column/Shear Wall- Work in progress.
BLOCK-2 (TOWER D)
1. Piling Work: - A) Piling -100% Done.
2. Excavation : 95% Done .
3. Pile Head Breaking & Pile Integrity Test : - 95% .
4. Sand Filling & Compaction:- 100% Done
5. Raft Bottom PCC Work - 100 % Done .
BLOCK-2 (TOWER E)
1. Piling Work: - A) Piling -100% Done.
2. Excavation : 100% Done .
3. Pile Head Breaking & Pile Integrity Test : - 100%.
4. Sand Filling & Compaction:- Work in Progress.
5. Raft Bottom PCC Work - Work in Progress .