AS ON 01.04.2026

    BLOCK-1 (TOWER A)
  • 1. Sub Structure Work - 100% Done
  • 2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
  • 3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
  • 4. 2nd Slab With Mivan Setting Flats - Work in Progress.

    BLOCK-1 (TOWER B)
  • 1. Sub Structure Work - 100% Done
  • 2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
  • 3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
  • 4. 2nd Slab With Mivan Setting Flats - Work in Progress.

    BLOCK-1 (TOWER C)
  • 1. Sub Structure Work - 100% Done
  • 2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
  • 3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
  • 4. 2nd Slab With Mivan Setting Flats - Work in Progress.

    BLOCK-2 (TOWER D)
  • 1) Piling Work: - A) Piling - 183 Nos Done Out Of 189 Nos.
    BLOCK-2 (TOWER E)
  • 1) Piling Work: - A) Piling - 115 Nos Done Out Of 125 Nos.