AS ON 01.07.2026

    BLOCK-1 (TOWER A)
  • 1. Sub Structure Work - 100% Done
  • 2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
  • 3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
  • 4. 2nd Slab With Mivan Setting Flats - Work in Progress.
  • 5. 2nd Slab With Conventional Area - 100 % Done.
  • 6. 2nd Slab to 3rd Slab Level Column/Shear Wall- Work in progress.
    BLOCK-1 (TOWER B)
  • 1. Sub Structure Work - 100% Done
  • 2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
  • 3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
  • 4. 2nd Slab With Mivan Setting Flats - Work in Progress.
  • 5. 2nd Slab With Conventional Area - 100 % Done.
  • 6. 2nd Slab to 3rd Slab Level Column/Shear Wall- Work in progress.
    BLOCK-1 (TOWER C)
  • 1. Sub Structure Work - 100% Done
  • 2. Plinth Level to 1st Slab - A) 1ST Slab : 100% Done
  • 3. 1st Slab to 2nd Slab Level Column/Shear Wall- 100% Done
  • 4. 2nd Slab With Mivan Setting Flats - Work in Progress.
  • 5. 2nd Slab With Conventional Area - 100 % Done.
  • 6. 2nd Slab to 3rd Slab Level Column/Shear Wall- Work in progress.
    BLOCK-2 (TOWER D)
  • 1. Piling Work: - A) Piling -100% Done.
  • 2. Excavation : 95% Done .
  • 3. Pile Head Breaking & Pile Integrity Test : - 95% .
  • 4. Sand Filling & Compaction:- 100% Done
  • 5. Raft Bottom PCC Work - 100 % Done .
    BLOCK-2 (TOWER E)
  • 1. Piling Work: - A) Piling -100% Done.
  • 2. Excavation : 100% Done .
  • 3. Pile Head Breaking & Pile Integrity Test : - 100%.
  • 4. Sand Filling & Compaction:- Work in Progress.
  • 5. Raft Bottom PCC Work - Work in Progress .