AS ON 01.10.2025

    BLOCK-1 (TOWER A,B,C)
    Foundation Work
  • A. Excavation & Soil dressing 98% done.
  • B. Pile head breaking & developed 98% done.
  • C. Sand filling 50% done.
  • D. PCC 30% done.
  • E. Reinforcement work in progress.