AS ON 01.01.2026

    BLOCK-1 (TOWER A)
    Sub Structure Work
  • A. Raft Reinforcement Work - 100% Done.
  • B. Raft Casting - 100 % Done.
  • C. Raft to Tie beam Level Column - 100% done.
  • D. Tie Beam Work - 100% done.

  • Plinth Level to 1st Slab
  • A) Column Work - Work in Progress.
    BLOCK-1 (TOWER B)
    Sub Structure Work
  • A. Raft Reinforcement Work - 100% Done.
  • B. Raft Casting - 100 % Done.
  • C. Raft to Tie beam Level Column - 100% done.
  • D. Tie Beam Work - 30% done.

  • Plinth Level to 1st Slab
  • A) Column Work - Work in Progress.
    BLOCK-1 (TOWER C)
    Sub Structure Work
  • A. Raft Reinforcement Work - 100% Done.
  • B. Raft Casting - 60 % Done.
  • C. Raft to Tie beam Level Column - 30% done.
  • D. Tie Beam Work in Progress.