AS ON 01.01.2026
BLOCK-1 (TOWER A)
Sub Structure Work
A. Raft Reinforcement Work - 100% Done.
B. Raft Casting - 100 % Done.
C. Raft to Tie beam Level Column - 100% done.
D. Tie Beam Work - 100% done.
Plinth Level to 1st Slab
A) Column Work - Work in Progress.
BLOCK-1 (TOWER B)
Sub Structure Work
A. Raft Reinforcement Work - 100% Done.
B. Raft Casting - 100 % Done.
C. Raft to Tie beam Level Column - 100% done.
D. Tie Beam Work - 30% done.
Plinth Level to 1st Slab
A) Column Work - Work in Progress.
BLOCK-1 (TOWER C)
Sub Structure Work
A. Raft Reinforcement Work - 100% Done.
B. Raft Casting - 60 % Done.
C. Raft to Tie beam Level Column - 30% done.
D. Tie Beam Work in Progress.