AS ON 01.10.2025
PHASE-I
CLUSTER - 03 (BUNGALOW HOUSE NO. 11 - 15)
Civil sub structure works completed.
Ground floor slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork completed.
Plastering work completed
Internal Electrical Wiring work completed.
Internal Plumbing work in progress.
Water Proofing is completed.
Pop work is completed.
Anti termite work completed.
Flooring work is completed.
Finishing work is completed.
External paint is completed.
CLUSTER - 04 (BUNGALOW HOUSE NO. 16 - 21)
Civil Sub structure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Brickwork is completed.
Roof slab is completed.
Electrical work is completed.
Internal Plumbing completed.
Plastering work is completed.
Anti termite work completed.
Waterproofing completed.
Flooring work completed.
Finishing work completed.
External paint completed.
CLUSTER - 15 (BUNGALOW HOUSE NO. 57 - 59)
Civil Sub structure works foundation completed.
Ground Floor slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork completed.
Plastering work completed.
Internal Electrical wiring work is completed.
Internal Plumbing work in completed.
Water Proofing work completed.
POP work completed.
Anti termite work completed.
Flooring work completed.
Finishing work completed.
External paint completed.
CLUSTER - 16 (BUNGALOW HOUSE NO. 34 - 37)
Civil Sub structure works completed.
Civil superstructure works completed.
Ground floor slab completed.
1st floor slab is completed.
Roof slab completed.
Brickwork is completed.
Plastering work completed.
Internal Plumbing work completed.
Internal Electrical Work completed.
Water Proofing completed.
Pop work completed.
Anti termite work completed.
Flooring work completed.
Finishing work completed.
External paint work completed.
CLUSTER - 17 (BUNGALOW HOUSE NO. 26 - 33)
Civil Sub structure works foundation completed.
Ground floor slab completed.
Brickwork in completed.
1st floor slab completed.
Internal Electrical work completed.
Roof slab is completed.
Plastering work is completed.
Internal Plumbing work completed.
Anti termite work completed.
Water Proofing work completed.
Flooring work is completed.
External paint work is completed.
Finishing work is completed.
CLUSTER - 19 (BUNGALOW HOUSE NO. 38 - 47)
Civil Sub structure works completed.
Civil superstructure works completed.
Ground floor slab completed.
1st floor slab is completed.
Roof slab completed.
Brickwork is completed.
Plastering work completed.
Internal Plumbing work completed.
Internal Electrical Work completed.
Water Proofing completed.
Pop work completed.
Anti termite work completed.
Flooring work completed.
Finishing work completed.
External paint work completed.
CLUSTER - 20 (BUNGALOW HOUSE NO. 48 - 56)
Civil Sub structure works completed.
Civil superstructure works completed.
Ground floor slab completed.
1st floor slab is completed.
Roof slab completed.
Brickwork is completed.
Plastering work completed.
Internal Plumbing work completed.
Internal Electrical Work completed.
Water Proofing completed.
Pop work completed.
Anti termite work completed.
Flooring work completed.
Finishing work completed.
External paint work completed.
CLUSTER - 21 (BUNGALOW HOUSE NO. 63 - 70)
Civil Sub structure works completed.
Civil superstructure works completed.
Ground floor slab completed.
1st floor slab is completed.
Roof slab completed.
Brickwork is completed.
Plastering work completed.
Internal Plumbing work completed.
Internal Electrical Work completed.
Water Proofing completed.
Pop work completed.
Anti termite work completed.
Flooring work is in completed (63 to 70).
Finishing work is in progress.
External paint work completed.
CLUSTER - 22 (BUNGALOW HOUSE NO. 71 - 78)
Civil Sub structure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork is completed.
Internal Electrical work is completed.
Plastering work is completed.
Internal Plumbing work is completed.
Pop work in progress.
Anti termite work completed.
Waterproofing work is completed.
Flooring work is in progress.(71 to 78)
Finishing work in progress (71,72,73,74,76,75,77,78).
External paint is completed.
CLUSTER - 23 (BUNGALOW HOUSE NO. 87 - 92)
Civil Sub structure works foundation completed.
Ground Floor Slab completed.
1st floor slab completed.
Roof slab completed.
Brickwork work is completed ( 87 to 92).
Internal Electrical work is completed.
Plumbing work is completed.
Plastering work is completed.
Anti termite work completed.
Waterproofing work is completed.
Flooring work is completed (87 to 92)
Finishing work is completed.
External paint is completed.
CLUSTER - 29 (BUNGALOW HOUSE NO. 98 - 99)
Sub structure works is completed.
Ground floor slab is completed.
Brick work is completed.
1st floor slab completed.
Roof slab completed.
Internal Electrical work is completed.
Plaster work is completed.
Plumbing work is completed.
Flooring work is completed.
Finishing work is completed.
External paint is completed.
CLUSTER - 30 (BUNGALOW HOUSE NO. 93 - 97)
Civil Sub structure works completed.
Ground Floor Slab completed.
1st floor slab completed.
Roof slab is completed.
Brick work is completed.
Internal Electrical work is completed
Plaster work is completed.
Plumbing work is completed
Anti termite work completed.
Waterproofing completed.
Flooring work is completed (93 to 97).
Finishing work is completed.
External paint is completed.
CLUSTER - 31 (BUNGALOW HOUSE NO. 83 - 86)
Civil Sub structure works foundation completed.
Ground Floor Slab completed.
1st floor slab completed.
Brick work is completed.
Roof slab is completed.
Plaster work is done.
Anti termite work completed.
Waterproofing work is done.
Flooring work is completed.
Finishing work is completed.
External paint is completed.
CLUSTER - 32 (BUNGALOW HOUSE NO. 79 - 82)
Civil Sub structure works foundation completed.
Ground Floor Slab completed.
1st floor slab completed
Brickwork in progress.
Internal Electrical work is completed.
Roof slab is completed.
Plastering work done.
Internal Plumbing work is completed.
Mumty room slab completed.
Anti termite work completed.
Flooring work is in progress.
Waterproofing work is completed.
Finishing work is completed.
External paint is completed.
CLUSTER - 33 (BUNGALOW HOUSE NO. 60 - 62)
Civil Sub structure works foundation completed.
Ground floor slab completed.
1st floor slab completed.
Brickwork is completed
Roof slab is completed.
Internal Electrical work is completed.
Plastering work is done.
Plumbing work is completed
Anti termite work completed.
Waterproofing is completed.
Finishing work is completed.
Flooring work is completed
External paint work is completed.
CLUB
Piling completed.
Excavation work in completed.
Raft is Completed.
Retaining Wall completed.
Ground floor slab completed.
1st floor slab is completed.
Brickwork is in progress.
2nd floor slab is completed.
Plaster work is in progress.
Roof slab is completed.
POP work is in progress.
Aluminium work is in progress.
Fire work is in progress.
Waterproofing work is in progress.
Electrical work is in progress.
Plumbing work is in progress.
Flooring work is in progress.
Internal paint work is in progress.
External paint work is in progress.
ROAD
Flooring work of road is completed at cl-3 & 4 ,cl-17 & 19, cl-15 & 33, cl-20 & 21, cl-22 & 23, cl-31 & 32, cl-29 & 30.
Landscape work is completed.
Road Flooring work is in progress in front of club.
PHASE-II
CLUSTER - 5 (Unit no. 204 TO 211)
Pile works is in completed.
Sub structure works is in progress.
CLUSTER - 6 (Unit no. 190 to 203)
Pile works is completed.
Sub structure works is in progress.
CLUSTER - 7 (Unit no. 184 to 189)
Pile works is completed.
Sub structure works is in progress.
CLUSTER - 8 (Unit no. 181 - 183)
Pile works is completed.
Sub structure works is in progress.
CLUSTER - 9 (Unit no. 175 - 180)
Pile works is completed.
Sub structure works is in progress.
CLUSTER - 13 (Unit no. 131 - 151 & 212)
Pile works is completed (147 to 151 & 212).
Pile work is in progress.(131 to 146).
CLUSTER - 14 (Unit no. 127 - 136)
Civil sub structure work is in progress(132 to 134).
CLUSTER - 15 (Unit no. 122 - 126)
Civil sub structure work is completed (122 to 126).
Ground floor slab completed. (122 to 126)
1st floor work is completed.(122 to 126)
Brick work is in progress.
Roof slab is completed.
Plaster work is in progress.
CLUSTER - 23 (Unit no. 174)
Civil sub structure work is completed.
Ground floor slab is completed.
1st floor slab is completed.
Roof slab is completed.
Brick work is done.
Electrical work is in progress.
Plaster work is in progress.
Plumbing work is in progress.
Waterproofing work is in progress.
Flooring work is in progress.
CLUSTER - 24 (Unit no. 158 - 162)
Pile works is completed.
CLUSTER - 25 (Unit no. 163 - 167)
Pile works is completed.
Sub structure is in progress.
CLUSTER - 26 (Unit no. 168 - 173)
Pile works is completed.
Sub structure is in progress.
CLUSTER - 27 (Unit no. 152 - 157)
Pile works is completed.
CLUSTER - 28 (Unit no. 100 - 105)
Pile works is completed.
Sub structure is in progress.
CLUSTER - 29 (Unit no. 106 - 109)
Pile works is completed.
Sub structure work is completed.
Ground floor slab completed.
1st floor slab is completed.(106 & 109)
Roof slab is completed.
Brick work is in progress.
Plaster work is in progress.
CLUSTER - 30 (Unit no. 110 TO 111)
Civil sub structure work completed.
Ground floor slab completed.
1st floor slab is completed.
Brick work is started.
Roof slab is completed.
Plaster work is in progress.
External paint work is in progress.
CLUSTER - 31 (Unit no. 112 TO 114)
Civil sub structure work is in progress.
Ground floor slab is completed.
1st floor slab is completed.
Brick work is in progress.
Roof slab is completed.
CLUSTER - 32 (Unit no. 115 - 118)
Sub structure (foundation) is completed.
Ground floor slab is completed.
1st floor slab is completed.
Roof slab is completed.
Brick work is in progress.
Electrical work is in progress.
Plaster work is no progress.
CLUSTER - 33 (Unit no. 119 TO 121)
Civil sub structure work is in progress.
Ground floor slab is completed.
1st floor slab is completed.
Brickwork is in progress.
Roof slab is completed.