AS ON 01.10.2025

    PHASE-I
    CLUSTER - 03 (BUNGALOW HOUSE NO. 11 - 15)
  • Civil sub structure works completed.
  • Ground floor slab completed.
  • 1st floor slab completed.
  • Roof slab completed.
  • Brickwork completed.
  • Plastering work completed
  • Internal Electrical Wiring work completed.
  • Internal Plumbing work in progress.
  • Water Proofing is completed.
  • Pop work is completed.
  • Anti termite work completed.
  • Flooring work is completed.
  • Finishing work is completed.
  • External paint is completed.
    CLUSTER - 04 (BUNGALOW HOUSE NO. 16 - 21)
  • Civil Sub structure works foundation completed.
  • Ground floor slab completed.
  • 1st floor slab completed.
  • Brickwork is completed.
  • Roof slab is completed.
  • Electrical work is completed.
  • Internal Plumbing completed.
  • Plastering work is completed.
  • Anti termite work completed.
  • Waterproofing completed.
  • Flooring work completed.
  • Finishing work completed.
  • External paint completed.
    CLUSTER - 15 (BUNGALOW HOUSE NO. 57 - 59)
  • Civil Sub structure works foundation completed.
  • Ground Floor slab completed.
  • 1st floor slab completed.
  • Roof slab completed.
  • Brickwork completed.
  • Plastering work completed.
  • Internal Electrical wiring work is completed.
  • Internal Plumbing work in completed.
  • Water Proofing work completed.
  • POP work completed.
  • Anti termite work completed.
  • Flooring work completed.
  • Finishing work completed.
  • External paint completed.
    CLUSTER - 16 (BUNGALOW HOUSE NO. 34 - 37)
  • Civil Sub structure works completed.
  • Civil superstructure works completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.
  • Roof slab completed.
  • Brickwork is completed.
  • Plastering work completed.
  • Internal Plumbing work completed.
  • Internal Electrical Work completed.
  • Water Proofing completed.
  • Pop work completed.
  • Anti termite work completed.
  • Flooring work completed.
  • Finishing work completed.
  • External paint work completed.
    CLUSTER - 17 (BUNGALOW HOUSE NO. 26 - 33)
  • Civil Sub structure works foundation completed.
  • Ground floor slab completed.
  • Brickwork in completed.
  • 1st floor slab completed.
  • Internal Electrical work completed.
  • Roof slab is completed.
  • Plastering work is completed.
  • Internal Plumbing work completed.
  • Anti termite work completed.
  • Water Proofing work completed.
  • Flooring work is completed.
  • External paint work is completed.
  • Finishing work is completed.
    CLUSTER - 19 (BUNGALOW HOUSE NO. 38 - 47)
  • Civil Sub structure works completed.
  • Civil superstructure works completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.
  • Roof slab completed.
  • Brickwork is completed.
  • Plastering work completed.
  • Internal Plumbing work completed.
  • Internal Electrical Work completed.
  • Water Proofing completed.
  • Pop work completed.
  • Anti termite work completed.
  • Flooring work completed.
  • Finishing work completed.
  • External paint work completed.
    CLUSTER - 20 (BUNGALOW HOUSE NO. 48 - 56)
  • Civil Sub structure works completed.
  • Civil superstructure works completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.
  • Roof slab completed.
  • Brickwork is completed.
  • Plastering work completed.
  • Internal Plumbing work completed.
  • Internal Electrical Work completed.
  • Water Proofing completed.
  • Pop work completed.
  • Anti termite work completed.
  • Flooring work completed.
  • Finishing work completed.
  • External paint work completed.
    CLUSTER - 21 (BUNGALOW HOUSE NO. 63 - 70)
  • Civil Sub structure works completed.
  • Civil superstructure works completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.
  • Roof slab completed.
  • Brickwork is completed.
  • Plastering work completed.
  • Internal Plumbing work completed.
  • Internal Electrical Work completed.
  • Water Proofing completed.
  • Pop work completed.
  • Anti termite work completed.
  • Flooring work is in completed (63 to 70).
  • Finishing work is in progress.
  • External paint work completed.
    CLUSTER - 22 (BUNGALOW HOUSE NO. 71 - 78)
  • Civil Sub structure works foundation completed.
  • Ground floor slab completed.
  • 1st floor slab completed.
  • Roof slab completed.
  • Brickwork is completed.
  • Internal Electrical work is completed.
  • Plastering work is completed.
  • Internal Plumbing work is completed.
  • Pop work in progress.
  • Anti termite work completed.
  • Waterproofing work is completed.
  • Flooring work is in progress.(71 to 78)
  • Finishing work in progress (71,72,73,74,76,75,77,78).
  • External paint is completed.
    CLUSTER - 23 (BUNGALOW HOUSE NO. 87 - 92)
  • Civil Sub structure works foundation completed.
  • Ground Floor Slab completed.
  • 1st floor slab completed.
  • Roof slab completed.
  • Brickwork work is completed ( 87 to 92).
  • Internal Electrical work is completed.
  • Plumbing work is completed.
  • Plastering work is completed.
  • Anti termite work completed.
  • Waterproofing work is completed.
  • Flooring work is completed (87 to 92)
  • Finishing work is completed.
  • External paint is completed.
    CLUSTER - 29 (BUNGALOW HOUSE NO. 98 - 99)
  • Sub structure works is completed.
  • Ground floor slab is completed.
  • Brick work is completed.
  • 1st floor slab completed.
  • Roof slab completed.
  • Internal Electrical work is completed.
  • Plaster work is completed.
  • Plumbing work is completed.
  • Flooring work is completed.
  • Finishing work is completed.
  • External paint is completed.
    CLUSTER - 30 (BUNGALOW HOUSE NO. 93 - 97)
  • Civil Sub structure works completed.
  • Ground Floor Slab completed.
  • 1st floor slab completed.
  • Roof slab is completed.
  • Brick work is completed.
  • Internal Electrical work is completed
  • Plaster work is completed.
  • Plumbing work is completed
  • Anti termite work completed.
  • Waterproofing completed.
  • Flooring work is completed (93 to 97).
  • Finishing work is completed.
  • External paint is completed.
    CLUSTER - 31 (BUNGALOW HOUSE NO. 83 - 86)
  • Civil Sub structure works foundation completed.
  • Ground Floor Slab completed.
  • 1st floor slab completed.
  • Brick work is completed.
  • Roof slab is completed.
  • Plaster work is done.
  • Anti termite work completed.
  • Waterproofing work is done.
  • Flooring work is completed.
  • Finishing work is completed.
  • External paint is completed.
    CLUSTER - 32 (BUNGALOW HOUSE NO. 79 - 82)
  • Civil Sub structure works foundation completed.
  • Ground Floor Slab completed.
  • 1st floor slab completed
  • Brickwork in progress.
  • Internal Electrical work is completed.
  • Roof slab is completed.
  • Plastering work done.
  • Internal Plumbing work is completed.
  • Mumty room slab completed.
  • Anti termite work completed.
  • Flooring work is in progress.
  • Waterproofing work is completed.
  • Finishing work is completed.
  • External paint is completed.
    CLUSTER - 33 (BUNGALOW HOUSE NO. 60 - 62)
  • Civil Sub structure works foundation completed.
  • Ground floor slab completed.
  • 1st floor slab completed.
  • Brickwork is completed
  • Roof slab is completed.
  • Internal Electrical work is completed.
  • Plastering work is done.
  • Plumbing work is completed
  • Anti termite work completed.
  • Waterproofing is completed.
  • Finishing work is completed.
  • Flooring work is completed
  • External paint work is completed.
    CLUB
  • Piling completed.
  • Excavation work in completed.
  • Raft is Completed.
  • Retaining Wall completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.
  • Brickwork is in progress.
  • 2nd floor slab is completed.
  • Plaster work is in progress.
  • Roof slab is completed.
  • POP work is in progress.
  • Aluminium work is in progress.
  • Fire work is in progress.
  • Waterproofing work is in progress.
  • Electrical work is in progress.
  • Plumbing work is in progress.
  • Flooring work is in progress.
  • Internal paint work is in progress.
  • External paint work is in progress.
    ROAD
  • Flooring work of road is completed at cl-3 & 4 ,cl-17 & 19, cl-15 & 33, cl-20 & 21, cl-22 & 23, cl-31 & 32, cl-29 & 30.
  • Landscape work is completed.
  • Road Flooring work is in progress in front of club.
    PHASE-II
    CLUSTER - 5 (Unit no. 204 TO 211)
  • Pile works is in completed.
  • Sub structure works is in progress.
    CLUSTER - 6 (Unit no. 190 to 203)
  • Pile works is completed.
  • Sub structure works is in progress.
    CLUSTER - 7 (Unit no. 184 to 189)
  • Pile works is completed.
  • Sub structure works is in progress.
    CLUSTER - 8 (Unit no. 181 - 183)
  • Pile works is completed.
  • Sub structure works is in progress.
    CLUSTER - 9 (Unit no. 175 - 180)
  • Pile works is completed.
  • Sub structure works is in progress.
    CLUSTER - 13 (Unit no. 131 - 151 & 212)
  • Pile works is completed (147 to 151 & 212).
  • Pile work is in progress.(131 to 146).
    CLUSTER - 14 (Unit no. 127 - 136)
  • Civil sub structure work is in progress(132 to 134).
    CLUSTER - 15 (Unit no. 122 - 126)
  • Civil sub structure work is completed (122 to 126).
  • Ground floor slab completed. (122 to 126)
  • 1st floor work is completed.(122 to 126)
  • Brick work is in progress.
  • Roof slab is completed.
  • Plaster work is in progress.
    CLUSTER - 23 (Unit no. 174)
  • Civil sub structure work is completed.
  • Ground floor slab is completed.
  • 1st floor slab is completed.
  • Roof slab is completed.
  • Brick work is done.
  • Electrical work is in progress.
  • Plaster work is in progress.
  • Plumbing work is in progress.
  • Waterproofing work is in progress.
  • Flooring work is in progress.
    CLUSTER - 24 (Unit no. 158 - 162)
  • Pile works is completed.
    CLUSTER - 25 (Unit no. 163 - 167)
  • Pile works is completed.
  • Sub structure is in progress.
    CLUSTER - 26 (Unit no. 168 - 173)
  • Pile works is completed.
  • Sub structure is in progress.
    CLUSTER - 27 (Unit no. 152 - 157)
  • Pile works is completed.
    CLUSTER - 28 (Unit no. 100 - 105)
  • Pile works is completed.
  • Sub structure is in progress.
    CLUSTER - 29 (Unit no. 106 - 109)
  • Pile works is completed.
  • Sub structure work is completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.(106 & 109)
  • Roof slab is completed.
  • Brick work is in progress.
  • Plaster work is in progress.
    CLUSTER - 30 (Unit no. 110 TO 111)
  • Civil sub structure work completed.
  • Ground floor slab completed.
  • 1st floor slab is completed.
  • Brick work is started.
  • Roof slab is completed.
  • Plaster work is in progress.
  • External paint work is in progress.
    CLUSTER - 31 (Unit no. 112 TO 114)
  • Civil sub structure work is in progress.
  • Ground floor slab is completed.
  • 1st floor slab is completed.
  • Brick work is in progress.
  • Roof slab is completed.
    CLUSTER - 32 (Unit no. 115 - 118)
  • Sub structure (foundation) is completed.
  • Ground floor slab is completed.
  • 1st floor slab is completed.
  • Roof slab is completed.
  • Brick work is in progress.
  • Electrical work is in progress.
  • Plaster work is no progress.
    CLUSTER - 33 (Unit no. 119 TO 121)
  • Civil sub structure work is in progress.
  • Ground floor slab is completed.
  • 1st floor slab is completed.
  • Brickwork is in progress.
  • Roof slab is completed.